Oracle IPM 10g and Imaging 11g Migration: Part 2

A couple weeks ago I wrote a post about ECM migrations, with a focus specifically on moving content from Oracle IPM/Imaging to other destination systems—projects we’ve been performing a lot of lately. Our tools of choice for migrations are ILINX Export and ILINX Import, but if the destination ECM system isn’t supported by ILINX Import, there are other options. Almost every ECM system has mechanisms to do bulk or mass imports. ILINX Export provides many options to format the data so sometimes it is a matter of configuring the output to be in a format supported by the third party import application. Other times, utilizing these third party import applications may require a little development. Regardless of what’s necessary, we’ve never run into a destination system that we couldn’t work with.

There are multiple reasons we split the migration operations into two parts—export and import—flexibility being the biggest one. There are a lot more options when splitting the migration into two separate operations. Since we don’t modify the data on export from the source system, a snapshot can be taken for long term archival. Then on import, or pre-import, we can massage the data, perform file conversions, or augment the data by pulling additional data from an external source. Even though we split the migration up into two operations, they can be run in tandem so there is little effect on the overall duration of the migration.

One of the biggest concerns surrounding these migrations is the amount of time it will take. Performing tests in the actual environment is required because of how many variables go into the throughput of a migration. If the migration is estimated to take too long after initial testing, there are options to address that scenario, including:

  • Create a migration environment with instances of the source ECM system software on newer, more powerful servers, and restore the production data to these new servers in order to execute the migration from there. This has the additional benefit of removing any potential performance impact to the legacy production system for the duration of the migration.
  • Spin up additional instances of ILINX Export and/or ILNX Import to increase throughput. There will be a point when additional instances of the export or import process will not increase throughput—generally when a bottleneck restricts the maximum throughput that the source or destination system can achieve.

Recently, I had a customer that had set a hard go-live date that was just 60 days after project initiation for their new system. We had no problem meeting this requirement from a technology deployment standpoint, but our migration testing indicated that we wouldn’t be able to move all of their 25+ million documents in that time frame. In order to make the new system go-live date, we migrated the three previous years’ content first, then resumed with the older, remaining content. Since the vast majority of content to be retrieved would be from the previous year, the fact that the migration wasn’t 100% complete at go-live was a non-issue. This is an approach we’ve followed numerous times.

Once a migration is in full swing, auditing can be the most time consuming part of the process. ILINX Export and ILINX Import have very complete auditing capabilities, so while the migration is occurring, issues are immediately identified and can be addressed. We generally audit a couple different ways to confirm success. If only using ILINX Export, what is exported can be compared with what is in the source system to ensure all content was pulled out. When performing a complete migration, what is imported into the destination system is compared with the source system. Any migration can only be considered a success when it is proven that all the content was migrated, which is why we practice multi-step auditing during the migration.

By following our standard methodology for migrations and utilizing the technology we’ve developed over the years, we consistently perform reliably successful migrations. To read more about migrations, review my previous blog posts Oracle IPM 10g and Imaging 11g Migration and Steps for a successful ECM migration using ILINX Export.

If you have any questions about my blogs, or would like to discuss the possibilities for migration within your organization, please reach out to me or your contact at ImageSource to start the conversation.

John Linehan
Sr. Systems Engineer
ImageSource, Inc.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s